Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026
| Project | Developer | DLD status | Built | DLD end date | Past DLD end date | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Sportz By Danube2845 · Al Hebiah Fourth · Dubai Sports City | Danube Properties Development L.L.C | Under construction | 80.2% | Mar 2026 7 mo past | 7 mo | 146 |
| Elitz By Danube2533 · Al Barsha South Fourth · Jumeirah Village Circle | Danube Properties Development L.L.C | Under construction | 91.8% | Dec 2025 10 mo past | 10 mo | 71 |
| Viewz 2 By Danube2560 · Al Thanyah Fifth · DMCC Master Community | Danube Properties Development L.L.C | Under construction | 65% | Jun 2026 4 mo past | 4 mo | 64 |
| Viewz 1 By Danube2554 · Al Thanyah Fifth · DMCC Master Community | Danube Properties Development L.L.C | Under construction | 66.5% | Jun 2026 4 mo past | 4 mo | 58 |
How to read this list
- DLD status
- Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
- Built
- The latest % complete that DLD publishes for the project.
- DLD end date
- The completion date in the DLD register, with whole months to go from the export date.
- Past DLD end date
- Whole months since the DLD end date, for projects DLD still lists as under construction.
- Sales, 24 mo
- Sales of units in the project registered with DLD in the last 24 months.