DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

1–17 of 17 projects, most registered sales in 24 months first

1–17 of 17 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date / completion Sales, 24 mo
La Violeta 22354 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Jul 2024 Completed 100
La Violeta 12348 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Feb 2025 Completed 91
Serena Casa Dora1791 · Wadi Al Safa 7 · 800 VillasNorth Dubailand Projects L.L.C Completed 100% May 2020 Completed 88
Villanova Amaranta1817 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% May 2022 Completed 81
Serena - Casa Viva1873 · Wadi Al Safa 7 · 800 VillasNorth Dubailand Projects L.L.C Completed 100% May 2021 Completed 63
La Rosa 62291 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Dec 2024 Completed 60
Villanova Amaranta B2077 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Jul 2021 Completed 58
Villanova Amaranta 32057 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Jun 2022 Completed 56
Serena Bella Casa1598 · Wadi Al Safa 7 · 800 VillasNorth Dubailand Projects L.L.C Completed 100% Oct 2019 Completed 55
Amaranta 22017 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Mar 2022 Completed 44
La Rosa Phase 22176 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Oct 2023 Completed 43
La Rosa 52272 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Aug 2024 Completed 28
La Rosa 32220 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Sep 2023 Completed 27
La Quinta1851 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Jul 2021 Completed 24
La Rosa 42234 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Feb 2022 Completed 19
Villanova Amaranta A2076 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Apr 2020 Completed 19
La Rosa2156 · Wadi Al Safa 5North Dubailand Projects L.L.C Completed 100% Oct 2023 Completed 16

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.