Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

1–6 of 6 projects, most registered sales in 24 months first

1–6 of 6 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date Sales, 24 mo
Capria West3525 · Wadi Al Safa 4Majid Al Futtaim Ghaf Woods L.L.C Under construction 1.2% May 2029 30 mo to go 716
Capria East3524 · Wadi Al Safa 4Majid Al Futtaim Ghaf Woods L.L.C Under construction 0.9% May 2029 30 mo to go 553
Distrikt3503 · Wadi Al Safa 4Majid Al Futtaim Ghaf Woods L.L.C Under construction 8.4% Sep 2028 22 mo to go 434
Lacina3336 · Wadi Al Safa 4Majid Al Futtaim Ghaf Woods L.L.C Under construction 20.8% Dec 2027 13 mo to go 331
Serra3076 · Wadi Al Safa 4Majid Al Futtaim Ghaf Woods L.L.C Under construction 42.1% — 184
Cilia3016 · Wadi Al Safa 4Majid Al Futtaim Ghaf Woods L.L.C Under construction 43.8% — 166

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.