DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

1–18 of 18 projects, most registered sales in 24 months first

1–18 of 18 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date Sales, 24 mo
Damac Riverside Views - Capri 13663 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 8.2% Mar 2029 28 mo to go 805
Damac Riverside Views - Azure 23661 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 5.8% Mar 2029 28 mo to go 695
Damac Riverside Views - Capri 23664 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 8.3% Mar 2029 28 mo to go 475
Damac Riverside Views - Royal 3&43669 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 13.4% Mar 2029 28 mo to go 449
Damac Riverside Views - Indigo 13665 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 12.1% Mar 2029 28 mo to go 439
Damac Riverside Views - Indigo 23666 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 12% Mar 2029 28 mo to go 346
Damac Riverside Views - Marine 23373 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 12% May 2028 18 mo to go 279
Damac Riverside Views - Marine 13372 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 11.8% May 2028 18 mo to go 275
Damac Riverside Views - Marine 33374 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 18.2% May 2028 18 mo to go 267
Damac Riverside Views - Marine 43375 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 21.2% May 2028 18 mo to go 259
Damac Riverside Views - Royal 13667 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 14% Mar 2029 28 mo to go 258
Damac Riverside Views - Royal 23668 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 13.5% Mar 2029 28 mo to go 258
Damac Riverside - Lush3169 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 41.7% Dec 2027 13 mo to go 249
Damac Riverside - Ivy3170 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 38.1% Dec 2027 13 mo to go 195
Damac Riverside - Olive3690 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 5.5% Jun 2028 19 mo to go 167
Damac Riverside - Sage3171 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 13.3% Dec 2027 13 mo to go 167
DAMAC Riverlink4349 · Dubai Investment Park SecondDamac Mry Investment L.L.C Not started 0.4% Mar 2029 28 mo to go 0
DAMAC Riverside Views - Azure 13660 · Dubai Investment Park SecondDamac Mry Investment L.L.C Under construction 5.5% Mar 2029 28 mo to go 0

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.