DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

3,451 of 3,486 on the map

243 projects243310 projects310445 projects445760 projects760140 projects140155 projects15530 projects30132 projects13228 projects28172 projects17286 projects8628 projects28156 projects15622 projects2246 projects4612 projects123 projects312 projects125 projects5DUBAI WATER FRONT VENETO · Completed61 projects6141 projects4135 projects3514 projects14MONTROSE · Completed45 projects4532 projects32117 projects1176 projects6BADRA PHASE 1 · Completed14 projects1459 projects59Park Gate Residences · Completed15 projects1532 projects3223 projects2314 projects14137 projects1373 projects36 projects6South Square · Under construction, 0–25% built3 projects32 projects2Project 4528 · Not startedProject 4579 · Not started1,459 projects1,459964 projects964460 projects460135 projects135103 projects103137 projects13719 projects195 projects540 projects406 projects621 projects2123 projects2362 projects6214 projects142 projects2Tilal Binghatti · Not started© OpenStreetMap contributors · Makani
Under construction, 0–25% built 25–50% built 50–75% built 75–100% built Not started Completed Approximate location (ringed) 35 of the 3,486 projects have no map location yet and are not shown.

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.