A M I S Real Estate Development L.L.C ايه ام اي اس للتطوير العقاري ش.ذ.م.م 3 projects in the DLD register: 0 completed, 3 under construction, 0 not started or pending. 1 of the 3 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 3- 0 units and villas in completed projects; 160 in projects not yet completed.
- Under construction past their DLD end date: 1 of 3 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by A M I S Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Woodland Terraces3457 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Under construction | 10.3% | Mar 2027 4 mo to go | — | 78 | 50 |
| Woodland Crest3547 · Nad Al Shiba First · Meydan Racecourse Community | Under construction | 1.4% | Jun 2027 7 mo to go | — | 52 | 33 |
| The Woodland Residences2854 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Under construction | 75.4% | Apr 2026 6 mo past | 6 mo | 30 | 2 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 3, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.