Ab Properties Limited أي بي بروبرتيز ليمتد 7 projects in the DLD register: 7 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026
Projects
7
in the DLD register
Completed
7
123 units delivered
Not yet completed
0
0 units in the pipeline
Delivery record
Projects: 7Completed 7
- Median time from start to completion: 24 months (7 completed projects).
- 123 units and villas in completed projects; 0 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 7 completed projects with both dates. In 7 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Ab Properties Limited Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Orchid Park403 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Sep 2011 Completed | 21 | 15 |
| Iris Park400 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | May 2011 Completed | 15 | 14 |
| Lilac Park404 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | May 2015 Completed | 17 | 11 |
| Mulberry Park402 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Apr 2011 Completed | 25 | 10 |
| Valencia405 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Aug 2010 Completed | 14 | 8 |
| Lotus Park401 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Oct 2010 Completed | 15 | 5 |
| Tulip Park406 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Nov 2010 Completed | 16 | 3 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.