Al Helal Al Zahaby Real Estate Development L.L.C الهلال الذهبى للتطوير العقاري ش.ذ.م.م 9 projects in the DLD register: 5 completed, 4 under construction, 0 not started or pending. 0 of the 4 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 9- Median time from start to completion: 21 months (5 completed projects).
- 448 units and villas in completed projects; 734 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 4 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 4 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Al Helal Al Zahaby Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Forest City Tower3330 · Wadi Al Safa 3 · Majan | Under construction | 70.1% | Apr 2027 5 mo to go | 253 | 211 |
| Sports View Residence By Al Helal Al Zahaby3277 · Warsan Fourth · International City Phase 3 | Completed | 100% | Jul 2026 Completed | 124 | 132 |
| Hz Residences 42879 · Warsan Fourth · International City Phase 3 | Completed | 100% | May 2025 Completed | 87 | 78 |
| Forest City Tower 23727 · Wadi Al Safa 5 · Dubai Land Residence Complex | Under construction | 1.2% | Jun 2027 7 mo to go | 194 | 68 |
| Oasis Residences3726 · Madinat Al Mataar · Dubai South Residential District | Under construction | 35.3% | Jul 2027 8 mo to go | 159 | 66 |
| Sports View Residence 2 By Al Helal Al Zahaby3836 · Warsan Fourth · International City Phase 3 | Under construction | 13.4% | Nov 2029 36 mo to go | 128 | 26 |
| Al Helal Al Zahaby Building1759 · Warsan Fourth · International City Phase 3 | Completed | 100% | Oct 2017 Completed | 81 | 18 |
| Al Helal Al Zahaby 21977 · Warsan Fourth · International City Phase 3 | Completed | 100% | Mar 2019 Completed | 89 | 17 |
| Al Helal Al Zahaby 32468 · Warsan Fourth · International City Phase 3 | Completed | 100% | Aug 2023 Completed | 67 | 13 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 4, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.