Al Madar Investment (L.L.C) المدار للاستثمارات (ذ.م.م) 3 projects in the DLD register: 3 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026
Projects
3
in the DLD register
Completed
3
682 units delivered
Not yet completed
0
0 units in the pipeline
Delivery record
Projects: 3Completed 3
- Median time from start to completion: 35 months (3 completed projects).
- 682 units and villas in completed projects; 0 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 3 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Al Madar Investment (L.L.C) Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Siraj Tower181 · Al Barshaa South Third · Arjan | Completed | 100% | Oct 2014 Completed | 374 | 167 |
| Burj View Residence1691 · Al Barshaa South Third · Arjan | Completed | 100% | Aug 2016 Completed | 120 | 81 |
| Scala Tower184 · Business Bay | Completed | 100% | Sep 2010 Completed | 188 | 69 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.