Al Mazaya Real Estate FZ-LLC المزايا العقارية منطقة حرة ذ.م.م 33 projects in the DLD register: 33 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026
Projects
33
in the DLD register
Completed
33
2,699 units delivered
Not yet completed
0
0 units in the pipeline
Delivery record
Projects: 33Completed 33
- Median time from start to completion: 63 months (33 completed projects).
- 2,699 units and villas in completed projects; 0 in projects not yet completed.
- Completed a month or more after their DLD end date: 2 of 33 completed projects with both dates. In 23 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Al Mazaya Real Estate FZ-LLC Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Qpoint LIWAN-PLOT R008 A&B1183 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Jun 2014 Completed | 230 | 53 |
| Qpoint LIWAN-PLOT R0051189 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | May 2014 Completed | 217 | 35 |
| Qpoint Liwan - Plot R0021185 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Dec 2014 Completed | 78 | 29 |
| Qpoint Liwan - Plot R0031187 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Apr 2014 Completed | 91 | 21 |
| Qpoint LIWAN-PLOT R0721204 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Oct 2013 Completed | 61 | 19 |
| Qpoint LIWAN-PLOT R0551201 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Oct 2014 Completed | 82 | 19 |
| Qpoint LIWAN-PLOT R0691223 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Sep 2013 Completed | 61 | 17 |
| Qpoint LIWAN-PLOT R0471195 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Apr 2014 Completed | 96 | 17 |
| Qpoint LIWAN-PLOT R0041188 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Aug 2014 Completed | 220 | 17 |
| Qpoint LIWAN-PLOT R0921210 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Nov 2013 Completed | 80 | 16 |
| Qpoint LIWAN-PLOT R0941205 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Nov 2013 Completed | 55 | 16 |
| Qpoint LIWAN-PLOT R0971215 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Jun 2014 Completed | 55 | 16 |
| Qpoint LIWAN- R0931208 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Jul 2014 Completed | 65 | 14 |
| Qpoint LIWAN-PLOT R0511196 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Nov 2014 Completed | 58 | 14 |
| Qpoint LIWAN-R0191192 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Jan 2014 Completed | 60 | 13 |
| Qpoint LIWAN-PLOT R0701224 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Aug 2013 Completed | 61 | 12 |
16 of 33 projectsAll 33 projects in the list
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.