DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Arabian Gulf Properties الخليج العربي للعقارات DLD developer no. 1013 · Registered with DLD on 12 June 2014 · Licence 671286 12 projects in the DLD register: 6 completed, 3 under construction, 3 not started or pending. 1 of the 3 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
12
in the DLD register
Completed
6
853 units delivered
Not yet completed
6
390 units in the pipeline
Past DLD end date
1 / 3
under construction with an end date

Delivery record

Projects: 12
Completed 6Under construction 3Not started or pending 3
  • Median time from start to completion: 18 months (6 completed projects).
  • 853 units and villas in completed projects; 390 in projects not yet completed.
  • Completed a month or more after their DLD end date: 1 of 6 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 1 of 3 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Arabian Gulf Properties Most registered sales in the last 24 months first

Projects by Arabian Gulf Properties
ProjectDLD status Built DLD end date / completion Past DLD end date Units Sales, 24 mo
Parkwood Residences2764 · Al Barsha South Fourth · Jumeirah Village Circle Under construction 57% Apr 2026 6 mo past6 mo 174 96
The Corner2904 · Wadi Al Safa 5 · Dubai Land Residence Complex Under construction 37.7% Jun 2027 7 mo to go— 126 96
Ag Tower1656 · Business Bay Completed 100% Jul 2021 Completed— 590 92
A 992768 · Wadi Al Safa 5 · Dubai Land Residence Complex Under construction 47.8% Oct 2026 under 1 mo past— 90 89
K11963 · Wadi Al Safa 5 · Dubai Land Residence Complex Completed 100% Nov 2021 Completed— 144 36
Edison House2023 · Wadi Al Safa 5 · Dubai Land Residence Complex Completed 100% Dec 2022 Completed— 65 21
Park Villa's 21536 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Feb 2016 Completed— 19 4
Park Villa's1535 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Dec 2015 Completed— 22 2
Project 3413, Wadi Al Safa 53413 · Wadi Al Safa 5 · Dubai Land Residence Complex Pending 0% Feb 2028 15 mo to go— — 0
Project 2903, Wadi Al Safa 52903 · Wadi Al Safa 5 · Dubai Land Residence Complex Pending 0% — — — 0
Project 2937, Al Barsha South Fourth2937 · Al Barsha South Fourth · Jumeirah Village Circle Pending 0% — — — 0
Park Villa's 61611 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Oct 2016 Completed— 13 0

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 6, all pinned

2 projects22 projects22 projects22 projects24 projects4Makani
25–50% built 50–75% built Not started

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.