B N H Real Estate Developer بي ان اتش للتطوير العقاري 7 projects in the DLD register: 5 completed, 2 under construction, 0 not started or pending. 2 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 7- Median time from start to completion: 20 months (5 completed projects).
- 894 units and villas in completed projects; 221 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 3 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 2 of 2 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by B N H Real Estate Developer Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Equiti Home2863 · Jabal Ali First · Al Furjan | Completed | 100% | Jan 2026 Completed | — | 302 | 212 |
| Equiti Gates2839 · Jabal Ali Industrial Second · Down Town Jabal Ali | Completed | 100% | Oct 2025 Completed | — | 284 | 146 |
| Equiti Garden3242 · Jabal Ali First · Al Furjan | Under construction | 87% | Dec 2025 10 mo past | 10 mo | 133 | 108 |
| Equiti Tower3185 · Warsan Fourth · International City Phase 3 | Under construction | 70.2% | Aug 2025 14 mo past | 14 mo | 88 | 88 |
| Equiti Apartments2496 · Warsan Fourth · International City Phase 3 | Completed | 100% | Dec 2022 Completed | — | 135 | 33 |
| Equiti Arcade2491 · Jabal Ali First · Al Furjan | Completed | 100% | Dec 2023 Completed | — | 83 | 22 |
| Equiti Residence2497 · Jabal Ali First · Al Furjan | Completed | 100% | Dec 2022 Completed | — | 90 | 17 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 2, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.