DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

B N H Real Estate Developer بي ان اتش للتطوير العقاري DLD developer no. 1219 · Registered with DLD on 15 October 2017 · Licence 787129 7 projects in the DLD register: 5 completed, 2 under construction, 0 not started or pending. 2 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
7
in the DLD register
Completed
5
894 units delivered
Not yet completed
2
221 units in the pipeline
Past DLD end date
2 / 2
under construction with an end date

Delivery record

Projects: 7
Completed 5Under construction 2
  • Median time from start to completion: 20 months (5 completed projects).
  • 894 units and villas in completed projects; 221 in projects not yet completed.
  • Completed a month or more after their DLD end date: 0 of 3 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 2 of 2 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by B N H Real Estate Developer Most registered sales in the last 24 months first

Projects by B N H Real Estate Developer
ProjectDLD status Built DLD end date / completion Past DLD end date Units Sales, 24 mo
Equiti Home2863 · Jabal Ali First · Al Furjan Completed 100% Jan 2026 Completed— 302 212
Equiti Gates2839 · Jabal Ali Industrial Second · Down Town Jabal Ali Completed 100% Oct 2025 Completed— 284 146
Equiti Garden3242 · Jabal Ali First · Al Furjan Under construction 87% Dec 2025 10 mo past10 mo 133 108
Equiti Tower3185 · Warsan Fourth · International City Phase 3 Under construction 70.2% Aug 2025 14 mo past14 mo 88 88
Equiti Apartments2496 · Warsan Fourth · International City Phase 3 Completed 100% Dec 2022 Completed— 135 33
Equiti Arcade2491 · Jabal Ali First · Al Furjan Completed 100% Dec 2023 Completed— 83 22
Equiti Residence2497 · Jabal Ali First · Al Furjan Completed 100% Dec 2022 Completed— 90 17

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 2, all pinned

EQUITI TOWER · 50–75% builtEQUITI GARDEN · 75–100% builtEQUITI TOWER · 50–75% builtEQUITI GARDEN · 75–100% builtMakani
50–75% built 75–100% built

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.