Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Binghatti Developers FZE بن غاطي للتطوير العقاري م م ح DLD developer no. 1051 · Registered with DLD on 6 January 2015 · Licence 1279 85 projects in the DLD register: 43 completed, 24 under construction, 18 not started or pending. 13 of the 23 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
85
in the DLD register
Completed
43
13,228 units delivered
Not yet completed
42
37,137 units in the pipeline
Past DLD end date
13 / 23
under construction with an end date

Delivery record

Projects: 85
Completed 43Under construction 24Not started or pending 18
  • Median time from start to completion: 16 months (43 completed projects).
  • 13,228 units and villas in completed projects; 37,137 in projects not yet completed.
  • Completed a month or more after their DLD end date: 6 of 37 completed projects with both dates. In 27 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 13 of 23 projects with an end date, by a median of 6 months.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Binghatti Developers FZE Most registered sales in the last 24 months first

Projects by Binghatti Developers FZE
ProjectDLD status Built DLD end date / completion Past DLD end date Units Sales, 24 mo
Binghatti Skyrise3349 · Business Bay Under construction 35.9% Dec 2026 1 mo to go— 3,358 3,281
Binghatti Elite3341 · Me'Aisem First · International Media Production Zone Under construction 53.3% Jun 2026 4 mo past4 mo 1,745 1,793
Binghatti Hillviews3321 · Al Barshaa South Second · Dubai Science Park Under construction 32.6% Apr 2026 7 mo past7 mo 1,575 1,556
Binghatti Vintage4102 · Wadi Al Safa 3 · Majan Not started 0% Mar 2027 4 mo to go— 1,572 1,522
Binghatti Aquarise3585 · Business Bay Under construction 21% Oct 2026 under 1 mo past— 1,592 1,348
Maybach Six4321 · Nad Al Shiba First · Meydan Racecourse Community Not started 0% Aug 2027 9 mo to go— 1,878 1,099
Binghatti Hills3053 · Al Barshaa South Second · Dubai Science Park Under construction 90% — — 1,701 1,085
Binghatti Skyflame 14393 · Wadi Al Safa 3 · Majan Not started 0% Dec 2027 13 mo to go— 1,407 913
Binghatti Skyterraces4327 · Al Hebiah First · Motor City Not started 0% Oct 2027 11 mo to go— 1,886 887
Binghatti Flare 014006 · Al Barsha South Fifth · Jumeirah Village Triangle Under construction 20% Jul 2027 8 mo to go— 845 793
Binghatti Circle3819 · Al Barsha South Fourth · Jumeirah Village Circle Under construction 22.1% May 2027 6 mo to go— 822 779
Binghatti Titania4104 · Wadi Al Safa 3 · Majan Not started 0% Feb 2027 3 mo to go— 789 727
Binghatti Ghost3192 · Al Jadaf · Dubai Health Care City Phase 2 Completed 100% Sep 2026 Completed— 785 706
Binghatti Apex3066 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Apr 2026 Completed— 552 662
Binghatti Skyhall3504 · Business Bay Under construction 31.1% Aug 2026 2 mo past2 mo 728 648
Binghatti Amberhall3552 · Al Barsha South Fourth · Jumeirah Village Circle Under construction 70% Feb 2026 8 mo past8 mo 710 623

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 42, all pinned

6 projects62 projects24 projects44 projects44 projects43 projects34 projects42 projects2Fendi Residences The Palm · Not started4 projects44 projects43 projects3Tilal Binghatti · Not started8 projects89 projects97 projects75 projects5Fendi Residences The Palm · Not started4 projects44 projects43 projects3Tilal Binghatti · Not startedMakani
Under construction, 0–25% built 25–50% built 50–75% built 75–100% built Not started Approximate location (ringed)

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.