Citi Developers Real Estate Development L.L.C سيتي ديفيلوبرز للتطوير العقاري ش.ذ.م.م 5 projects in the DLD register: 0 completed, 5 under construction, 0 not started or pending. 1 of the 5 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 5- 0 units and villas in completed projects; 719 in projects not yet completed.
- Under construction past their DLD end date: 1 of 5 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Citi Developers Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Allura Residences by Citi Developers3289 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 7.8% | Jul 2027 8 mo to go | — | 264 | 220 |
| Aveline Residences by Citi Developers2864 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 42.2% | Jul 2026 3 mo past | 3 mo | 265 | 168 |
| Arya Residences by Citi Developers3874 · Palm Deira | Under construction | 3% | Dec 2027 13 mo to go | — | 68 | 56 |
| Agua Residences by Citi Developers - Tower 13872 · Palm Deira | Under construction | 5% | Dec 2027 13 mo to go | — | 61 | 39 |
| Agua Residences by Citi Developers - Tower 23756 · Palm Deira | Under construction | 3.1% | Dec 2027 13 mo to go | — | 61 | 33 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 5, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.