Clear Vision Real Estate Development L.L.C كلير فيجن للتطوير العقاري ش.ذ.م.م 8 projects in the DLD register: 3 completed, 3 under construction, 2 not started or pending. 0 of the 3 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 8- Median time from start to completion: 16 months (3 completed projects).
- 282 units and villas in completed projects; 1,027 in projects not yet completed.
- Completed a month or more after their DLD end date: 1 of 2 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 3 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Clear Vision Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Vista by Vision4175 · Me'Aisem First · International Media Production Zone | Under construction | 12.2% | Sep 2027 10 mo to go | 328 | 309 |
| Verde By Vision4124 · Al Hebiah Fourth · Dubai Sports City | Under construction | 12% | Sep 2027 10 mo to go | 253 | 236 |
| Reem by vision3612 · Wadi Al Safa 2 · Liwan1 | Under construction | 70.4% | Dec 2026 1 mo to go | 200 | 192 |
| Celine By Vision3390 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Jan 2026 Completed | 104 | 142 |
| Sera Gardens by Vision4455 · Me'Aisem First · International Media Production Zone | Not started | 0% | Apr 2028 17 mo to go | 246 | 141 |
| Karma2934 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Jan 2025 Completed | 90 | 88 |
| Coral by Vision3037 · Al Satwa · Jumeirah Garden City | Completed | 100% | Feb 2026 Completed | 88 | 81 |
| Project 4567, Wadi Al Safa 24567 · Wadi Al Safa 2 · Liwan1 | Pending | 0% | Jul 2029 32 mo to go | — | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 5, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.