Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Crestarc Developers L.L.C كرستارك للتطوير العقاري ش.ذ.م.م DLD developer no. 2423 · Registered with DLD on 3 July 2025 · Licence 1522947 1 projects in the DLD register: 0 completed, 0 under construction, 1 not started or pending. DLD projects register, export of 1 November 2026

Projects
1
in the DLD register
Completed
0
0 units delivered
Not yet completed
1
939 units in the pipeline

Delivery record

Projects: 1
Not started or pending 1
  • 0 units and villas in completed projects; 939 in projects not yet completed.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Crestarc Developers L.L.C Most registered sales in the last 24 months first

Projects by Crestarc Developers L.L.C
ProjectDLD status Built DLD end date Units Sales, 24 mo
The Meriva Collection4346 · Palm Deira Not started 0.1% Dec 2031 61 mo to go 939 511

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 1, all pinned

THE MERIVA COLLECTION · Not startedTHE MERIVA COLLECTION · Not startedMakani
Not started Approximate location (ringed)

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.