Deval Real Estate Development L.L.C ديفال للتطوير العقاري ش.ذ.م.م 6 projects in the DLD register: 4 completed, 0 under construction, 2 not started or pending. DLD projects register, export of 1 November 2026
Delivery record
Projects: 6- Median time from start to completion: 17 months (4 completed projects).
- 395 units and villas in completed projects; 147 in projects not yet completed.
- Completed a month or more after their DLD end date: 1 of 4 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Deval Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Elegance by Chaimaa Holding2515 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Mar 2026 Completed | 118 | 30 |
| Chaimaa Avenue2183 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Jun 2020 Completed | 89 | 14 |
| Chaimaa Premiere1971 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Apr 2019 Completed | 96 | 13 |
| Chaimaa Avenue 22275 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Nov 2022 Completed | 92 | 13 |
| Symphony by Chaimaa3592 · Wadi Al Safa 3 · Majan | Not started | 0% | Aug 2027 9 mo to go | 71 | 10 |
| Isla Residences by Chaimaa Holding4344 · Palm Deira | Pending | 0% | Mar 2028 16 mo to go | 76 | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 2, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.