Falak Properties فلك للعقارات 6 projects in the DLD register: 6 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026
Projects
6
in the DLD register
Completed
6
894 units delivered
Not yet completed
0
0 units in the pipeline
Delivery record
Projects: 6Completed 6
- Median time from start to completion: 51 months (4 completed projects).
- 894 units and villas in completed projects; 0 in projects not yet completed.
- Completed a month or more after their DLD end date: 2 of 6 completed projects with both dates. In 4 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Falak Properties Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Hub Canal 1 Tower1301 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | Sep 2011 Completed | 210 | 49 |
| Hub Canal 2 Tower1302 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | Apr 2017 Completed | 180 | 44 |
| Cricket Tower1299 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | Sep 2016 Completed | 168 | 33 |
| Hockey Tower1300 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | Jul 2011 Completed | 168 | 27 |
| Tennis Tower1304 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | May 2010 Completed | 84 | 16 |
| Golf Tower1303 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | May 2010 Completed | 84 | 15 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.