Front Line Investment Management L.L.C شركة الخط الامامي لادارة الاستثمار ش.ذ.م.م 46 projects in the DLD register: 33 completed, 12 under construction, 1 not started or pending. 1 of the 6 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 46- Median time from start to completion: 63 months (33 completed projects).
- 2,200 units and villas in completed projects; 1,834 in projects not yet completed.
- Completed a month or more after their DLD end date: 2 of 32 completed projects with both dates. In 18 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 1 of 6 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Front Line Investment Management L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Damac Hills (2) - Violet 43288 · Madinat Hind 4 · Damac Hills 2 | Under construction | 14.2% | Aug 2027 9 mo to go | — | 762 |
| Damac Hills (2) - Violet 33222 · Madinat Hind 4 · Damac Hills 2 | Under construction | 36.2% | Jun 2027 7 mo to go | 1 | 631 |
| Damac Hills (2) - Elo 2 & Elo 33122 · Madinat Hind 4 · Damac Hills 2 | Under construction | 6.4% | Jun 2027 7 mo to go | 1,145 | 277 |
| Damac Hills (2) - Violet 23199 · Madinat Hind 4 · Damac Hills 2 | Under construction | 57.6% | Feb 2027 3 mo to go | — | 221 |
| Damac Hills (2) - Mulberry1679 · Madinat Hind 4 · Damac Hills 2 | Completed | 100% | Oct 2021 Completed | — | 200 |
| Damac Hills (2) - Camelia2548 · Madinat Hind 4 · Damac Hills 2 | Completed | 100% | Nov 2025 Completed | 578 | 158 |
| Damac Hills (2) - Vardon1767 · Madinat Hind 4 · Damac Hills 2 | Completed | 100% | Mar 2022 Completed | — | 151 |
| Damac Hills (2) - Pacifica1647 · Madinat Hind 4 · Damac Hills 2 | Completed | 100% | Feb 2022 Completed | — | 139 |
| Sold Without Project for Front Line Investment Managment1008 · Madinat Hind 4 · Damac Hills 2 | Not started | 0% | — | — | 136 |
| Damac Hills (2) - Violet2734 · Madinat Hind 4 · Damac Hills 2 | Under construction | 95.2% | — | — | 128 |
| Damac Hills (2) - Janusia1621 · Madinat Hind 4 · Damac Hills 2 | Completed | 100% | Feb 2020 Completed | — | 109 |
| Damac Hills (2) - Viridis1675 · Madinat Hind 4 · Damac Hills 2 | Completed | 100% | Apr 2023 Completed | 870 | 106 |
| Damac Hills (2) - Albizia1794 · Madinat Hind 4 · Damac Hills 2 | Completed | 100% | Mar 2022 Completed | — | 103 |
| Damac Hills (2) - Basswood1803 · Madinat Hind 4 · Damac Hills 2 | Completed | 100% | Mar 2022 Completed | — | 101 |
| Damac Hills (2) - Zinnia1595 · Madinat Hind 4 · Damac Hills 2 | Completed | 100% | Jun 2022 Completed | — | 86 |
| Damac Hills (2) - Sanctnary1640 · Madinat Hind 4 · Damac Hills 2 | Completed | 100% | Jun 2019 Completed | — | 84 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 13, 12 pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.