G F S Real Estate Development L.L.C جي اف اس للتطوير العقاري ش.ذ.م.م 2 projects in the DLD register: 0 completed, 1 under construction, 1 not started or pending. 0 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 2- 0 units and villas in completed projects; 506 in projects not yet completed.
- Under construction past their DLD end date: 0 of 1 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by G F S Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| GFS Coventry Gardens II3864 · Wadi Al Safa 5 · Dubai Land Residence Complex | Under construction | 1.3% | Nov 2027 12 mo to go | 134 | 45 |
| Coventry 24178 · Warsan Fourth · International City Phase 3 | Not started | 0% | Dec 2028 25 mo to go | 372 | 22 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 2, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.