DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Ginco Properties L.L.C جينكو العقارية ش.ذ.م.م DLD developer no. 1485 · Registered with DLD on 22 September 2022 · Licence 713526 4 projects in the DLD register: 2 completed, 1 under construction, 1 not started or pending. 0 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
4
in the DLD register
Completed
2
412 units delivered
Not yet completed
2
510 units in the pipeline
Past DLD end date
0 / 1
under construction with an end date

Delivery record

Projects: 4
Completed 2Under construction 1Not started or pending 1
  • 412 units and villas in completed projects; 510 in projects not yet completed.
  • Completed a month or more after their DLD end date: 1 of 2 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 0 of 1 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Ginco Properties L.L.C Most registered sales in the last 24 months first

Projects by Ginco Properties L.L.C
ProjectDLD status Built DLD end date / completion Units Sales, 24 mo
One Residence3150 · Burj Khalifa · DownTown Dubai Under construction 6.3% Mar 2027 4 mo to go 458 250
Vyb2727 · Business Bay Completed 100% Jun 2026 Completed 181 66
Prive Residence2529 · Hadaeq Sheikh Mohammed Bin Rashid · Dubai Hills Estate Completed 100% Oct 2023 Completed 231 59
Velor3392 · Business Bay Not started 0% Nov 2027 12 mo to go 52 0

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 2, all pinned

One Residence · Under construction, 0–25% builtVELOR · Not started2 projects2Makani
Under construction, 0–25% built Not started

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.