H A B N Real Estate Development L.L.C شركة اتش ايه بي ان للتطوير العقاري ش.ذ.م.م 2 projects in the DLD register: 0 completed, 2 under construction, 0 not started or pending. 2 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 2- 0 units and villas in completed projects; 926 in projects not yet completed.
- Under construction past their DLD end date: 2 of 2 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by H A B N Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| The Wind Tower I398 · Al Thanyah Fifth · DMCC Master Community | Under construction | 74.6% | Jun 2023 40 mo past | 40 mo | 515 | 38 |
| The Wind Tower Ii399 · Al Thanyah Fifth · DMCC Master Community | Under construction | 84.5% | Jun 2023 40 mo past | 40 mo | 411 | 19 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 2, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.