Hre Real Estate Development L.L.C أتش أر أي للتطوير العقاري ش.ذ.م.م 6 projects in the DLD register: 1 completed, 5 under construction, 0 not started or pending. 2 of the 5 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 6- 1,145 units and villas in completed projects; 4,428 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 1 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 2 of 5 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Hre Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Skyhills Astra by HRE3480 · Al Barshaa South Second · Dubai Science Park | Under construction | 47.1% | Jun 2028 19 mo to go | — | 1,911 | 1,555 |
| Skyhills II by HRE3057 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 96% | Jun 2026 5 mo past | 5 mo | 526 | 481 |
| Skyhills III by HRE3058 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 75.7% | Jun 2026 5 mo past | 5 mo | 513 | 418 |
| Skyhills I by HRE1643 · Al Barshaa South Second · Dubai Science Park | Completed | 100% | Jul 2026 Completed | — | 1,145 | 252 |
| Sakura Gardens by HRE4111 · Wadi Al Safa 2 · Falcon City | Under construction | 3.6% | Jun 2029 31 mo to go | — | 1,429 | 229 |
| Celeste3527 · Al Jadaf · Jaddaf Waterfront | Under construction | 3% | Feb 2027 3 mo to go | — | 49 | 31 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 5, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.