Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Iman Developers L.L.C إيمان للتطوير ذ.م.م DLD developer no. 1178 · Registered with DLD on 8 March 2017 · Licence 768225 18 projects in the DLD register: 8 completed, 7 under construction, 3 not started or pending. 1 of the 6 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
18
in the DLD register
Completed
8
1,176 units delivered
Not yet completed
10
3,438 units in the pipeline
Past DLD end date
1 / 6
under construction with an end date

Delivery record

Projects: 18
Completed 8Under construction 7Not started or pending 3
  • Median time from start to completion: 21 months (8 completed projects).
  • 1,176 units and villas in completed projects; 3,438 in projects not yet completed.
  • Completed a month or more after their DLD end date: 1 of 8 completed projects with both dates. In 6 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 1 of 6 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Iman Developers L.L.C Most registered sales in the last 24 months first

Projects by Iman Developers L.L.C
ProjectDLD status Built DLD end date / completion Past DLD end date Units Sales, 24 mo
One Sky Park By Iman3179 · Al Barsha South Fourth · Jumeirah Village Circle Under construction 21.7% Mar 2028 16 mo to go— 584 549
Sierra By Iman3835 · Al Hebiah First · Motor City Under construction 3.7% Jun 2029 31 mo to go— 598 544
15 Cascade3528 · Al Hebiah First · Motor City Under construction 5.5% Sep 2028 22 mo to go— 442 409
One Park Square By Iman3366 · Al Barsha South Fourth · Jumeirah Village Circle Under construction 20.1% Jun 2028 19 mo to go— 269 258
Oxford Cove4330 · Al Barsha South Fourth · Jumeirah Village Circle Not started 0% Mar 2029 28 mo to go— 253 162
Oxford Gardens2703 · Al Barshaa South Third · Arjan Completed 100% Sep 2025 Completed— 240 124
10 OXFORD by IMAN2837 · Al Barsha South Fourth · Jumeirah Village Circle Under construction 91.3% — — 430 101
One Park Central By Iman2969 · Al Barsha South Fourth · Jumeirah Village Circle Under construction 20.1% Jun 2027 7 mo to go— 526 87
113 Residences4503 · Al Safouh First · Sufouh Gardens Not started 0% Feb 2029 27 mo to go— 113 58
The Grove By Iman2512 · Hadaeq Sheikh Mohammed Bin Rashid · Dubai Hills Estate Completed 100% Aug 2024 Completed— 125 58
Oxford Terraces 22600 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Nov 2024 Completed— 101 55
Oxford 2122321 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Feb 2023 Completed— 212 53
Gardens 22938 · Al Barshaa South Third · Arjan Under construction 68.5% Dec 2025 10 mo past10 mo 223 50
Oxford Terraces2393 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Jan 2024 Completed— 117 36
Oxford Residence 22080 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Mar 2020 Completed— 147 33
Oxford Boulevard2204 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Oct 2021 Completed— 131 27

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 10, all pinned

10 OXFORD by IMAN · 75–100% built2 projects2ONE PARK CENTRAL BY IMAN · Under construction, 0–25% builtONE SKY PARK BY IMAN · Under construction, 0–25% builtONE PARK SQUARE BY IMAN · Under construction, 0–25% built2 projects2OXFORD COVE · Not started113 RESIDENCES · Not started5 projects52 projects22 projects2113 RESIDENCES · Not startedMakani
Under construction, 0–25% built 50–75% built 75–100% built Not started

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.