Iman Developers L.L.C إيمان للتطوير ذ.م.م 18 projects in the DLD register: 8 completed, 7 under construction, 3 not started or pending. 1 of the 6 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 18- Median time from start to completion: 21 months (8 completed projects).
- 1,176 units and villas in completed projects; 3,438 in projects not yet completed.
- Completed a month or more after their DLD end date: 1 of 8 completed projects with both dates. In 6 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 1 of 6 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Iman Developers L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| One Sky Park By Iman3179 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 21.7% | Mar 2028 16 mo to go | — | 584 | 549 |
| Sierra By Iman3835 · Al Hebiah First · Motor City | Under construction | 3.7% | Jun 2029 31 mo to go | — | 598 | 544 |
| 15 Cascade3528 · Al Hebiah First · Motor City | Under construction | 5.5% | Sep 2028 22 mo to go | — | 442 | 409 |
| One Park Square By Iman3366 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 20.1% | Jun 2028 19 mo to go | — | 269 | 258 |
| Oxford Cove4330 · Al Barsha South Fourth · Jumeirah Village Circle | Not started | 0% | Mar 2029 28 mo to go | — | 253 | 162 |
| Oxford Gardens2703 · Al Barshaa South Third · Arjan | Completed | 100% | Sep 2025 Completed | — | 240 | 124 |
| 10 OXFORD by IMAN2837 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 91.3% | — | — | 430 | 101 |
| One Park Central By Iman2969 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 20.1% | Jun 2027 7 mo to go | — | 526 | 87 |
| 113 Residences4503 · Al Safouh First · Sufouh Gardens | Not started | 0% | Feb 2029 27 mo to go | — | 113 | 58 |
| The Grove By Iman2512 · Hadaeq Sheikh Mohammed Bin Rashid · Dubai Hills Estate | Completed | 100% | Aug 2024 Completed | — | 125 | 58 |
| Oxford Terraces 22600 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Nov 2024 Completed | — | 101 | 55 |
| Oxford 2122321 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Feb 2023 Completed | — | 212 | 53 |
| Gardens 22938 · Al Barshaa South Third · Arjan | Under construction | 68.5% | Dec 2025 10 mo past | 10 mo | 223 | 50 |
| Oxford Terraces2393 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Jan 2024 Completed | — | 117 | 36 |
| Oxford Residence 22080 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Mar 2020 Completed | — | 147 | 33 |
| Oxford Boulevard2204 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Oct 2021 Completed | — | 131 | 27 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 10, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.