Jumeirah Golf Estates L.L.C عقارات جميرا جولف ش.ذ.م.م 11 projects in the DLD register: 11 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026
Projects
11
in the DLD register
Completed
11
589 units delivered
Not yet completed
0
0 units in the pipeline
Delivery record
Projects: 11Completed 11
- Median time from start to completion: 39 months (11 completed projects).
- 589 units and villas in completed projects; 0 in projects not yet completed.
- Completed a month or more after their DLD end date: 3 of 11 completed projects with both dates. In 6 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Jumeirah Golf Estates L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Jumeirah Golf Estates1284 · Me'Aisem First · Jumeirah Golf Estates | Completed | 100% | Aug 2015 Completed | — | 50 |
| Alandalus1652 · Me'Aisem First · Jumeirah Golf Estates | Completed | 100% | Jun 2018 Completed | 215 | 47 |
| ALandalus Building D2060 · Me'Aisem First · Jumeirah Golf Estates | Completed | 100% | Apr 2020 Completed | 136 | 34 |
| AL Andalus Phase 21846 · Me'Aisem First · Jumeirah Golf Estates | Completed | 100% | Dec 2019 Completed | 120 | 25 |
| Redwood Avenue1723 · Me'Aisem First · Jumeirah Golf Estates | Completed | 100% | Dec 2016 Completed | — | 21 |
| Alandalus Building E2022 · Me'Aisem First · Jumeirah Golf Estates | Completed | 100% | Aug 2020 Completed | 89 | 18 |
| ALandalus Townhouse1856 · Me'Aisem First · Jumeirah Golf Estates | Completed | 100% | Apr 2020 Completed | — | 16 |
| Red Wood Park1584 · Me'Aisem First · Jumeirah Golf Estates | Completed | 100% | Jul 2018 Completed | — | 12 |
| Alandalus Building G2198 · Me'Aisem First · Jumeirah Golf Estates | Completed | 100% | Apr 2021 Completed | 29 | 12 |
| Redwood Park Phase21770 · Me'Aisem First · Jumeirah Golf Estates | Completed | 100% | Sep 2017 Completed | — | 9 |
| Flame Tree Ridge1709 · Me'Aisem First · Jumeirah Golf Estates | Completed | 100% | Jul 2016 Completed | — | 5 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.