Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Jumeirah Park (L.L.C) جميرا بارك (ش.ذ.م.م) DLD developer no. 880 · Registered with DLD on 13 July 2009 · Licence 588710 5 projects in the DLD register: 5 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026

Projects
5
in the DLD register
Completed
5
2,562 units delivered
Not yet completed
0
0 units in the pipeline

Delivery record

Projects: 5
Completed 5
  • Median time from start to completion: 28 months (5 completed projects).
  • 2,562 units and villas in completed projects; 0 in projects not yet completed.
  • Completed a month or more after their DLD end date: 1 of 5 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Jumeirah Park (L.L.C) Most registered sales in the last 24 months first

Projects by Jumeirah Park (L.L.C)
ProjectDLD status Built DLD end date / completion Units Sales, 24 mo
Jumeirah Park1282 · Al Thanyah Fifth · Jumeirah Park Completed 100% Jan 2014 Completed 1,787 195
Jumeirah Park Package 1A1485 · Al Thanyah Fifth · Jumeirah Park Completed 100% Sep 2015 Completed 247 34
Jumeirah Park 7A1369 · Al Thanyah Fifth · Jumeirah Park Completed 100% Jul 2015 Completed 218 25
Jumeirah Park 7B&C1368 · Al Thanyah Fifth · Jumeirah Park Completed 100% Feb 2016 Completed 176 24
Jumeirah Park - Package 5A1332 · Al Thanyah Fifth · Jumeirah Park Completed 100% Jun 2015 Completed 134 8

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.