Lootah Real Estate Development L.L.C لوتاه لتطوير العقارات ش.ذ.م.م 7 projects in the DLD register: 7 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026
Projects
7
in the DLD register
Completed
7
469 units delivered
Not yet completed
0
0 units in the pipeline
Delivery record
Projects: 7Completed 7
- Median time from start to completion: 28 months (7 completed projects).
- 469 units and villas in completed projects; 0 in projects not yet completed.
- Completed a month or more after their DLD end date: 1 of 7 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Lootah Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| LOCI Residences2216 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Mar 2023 Completed | 114 | 39 |
| Shamal Residences 21501 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | May 2016 Completed | 128 | 35 |
| Shamal Waves1807 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Dec 2018 Completed | 68 | 33 |
| Living Garden II2058 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | May 2021 Completed | 123 | 19 |
| Shamal Terraces 2962 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Mar 2012 Completed | 17 | 5 |
| Shamal Terraces 31497 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Nov 2015 Completed | 10 | 1 |
| Shamal Terraces 41498 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Feb 2015 Completed | 9 | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.