M I R A Developments L.L.C ام اي ار ايه للتطوير ش.ذ.م.م 4 projects in the DLD register: 0 completed, 3 under construction, 1 not started or pending. 1 of the 3 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 4- 0 units and villas in completed projects; 941 in projects not yet completed.
- Under construction past their DLD end date: 1 of 3 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by M I R A Developments L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Trussardi Residences 23556 · Jabal Ali First · Discovery Gardens | Under construction | 4.6% | Jul 2027 8 mo to go | — | 389 | 104 |
| Trussardi Residences2900 · Jabal Ali First · Al Furjan | Under construction | 36.2% | Jan 2026 9 mo past | 9 mo | 142 | 99 |
| Mira Villas designed by Bentley Home3128 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Under construction | 31.8% | Dec 2026 1 mo to go | — | 36 | 13 |
| John Richmond Residences4428 · Jabal Ali First · Discovery Gardens | Pending | 0% | Dec 2028 25 mo to go | — | 374 | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 4, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.