Majid Developments L.L.C مجيد للتطوير العقاري ش.ذ.م.م 4 projects in the DLD register: 0 completed, 2 under construction, 2 not started or pending. 1 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 4- 0 units and villas in completed projects; 333 in projects not yet completed.
- Under construction past their DLD end date: 1 of 2 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Majid Developments L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| ARLINGTON PARK By MAJID3747 · Wadi Al Safa 5 · Dubai Land Residence Complex | Under construction | 5.7% | Dec 2027 13 mo to go | — | 140 | 128 |
| Mayfair Gardens By Majid3207 · Al Satwa · Jumeirah Garden City | Under construction | 70.1% | Aug 2026 2 mo past | 2 mo | 64 | 49 |
| Arlington Park Ii By Majid4425 · Wadi Al Safa 5 · Dubai Land Residence Complex | Not started | 0% | Apr 2028 17 mo to go | — | 129 | 41 |
| Project 4550, Wadi Al Safa 54550 · Wadi Al Safa 5 · Dubai Land Residence Complex | Pending | 0% | Jun 2029 31 mo to go | — | — | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 4, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.