Marquis Home Developer L.L.C ماركيز هوم للتطوير العقاري ش.ذ.م.م 4 projects in the DLD register: 1 completed, 1 under construction, 2 not started or pending. 0 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 4- 126 units and villas in completed projects; 792 in projects not yet completed.
- Completed a month or more after their DLD end date: 1 of 1 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 1 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Marquis Home Developer L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Marquis One3702 · Al Barshaa South Third · Arjan | Not started | 0.3% | Dec 2028 25 mo to go | 489 | 397 |
| Marquis Horizon4372 · Madinat Al Mataar · Dubai South Residential District | Not started | 0% | Sep 2028 22 mo to go | 174 | 80 |
| Marquis Vista3632 · Wadi Al Safa 5 · Dubai Land Residence Complex | Under construction | 3.5% | Dec 2027 13 mo to go | 129 | 77 |
| Marquis Galleria2591 · Al Barshaa South Third · Arjan | Completed | 100% | Apr 2026 Completed | 126 | 52 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 3, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.