Meraki Real Estate Development L.L.C ميراكي للتطوير العقاري ش.ذ.م.م 6 projects in the DLD register: 2 completed, 2 under construction, 2 not started or pending. 0 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 6- 526 units and villas in completed projects; 924 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 2 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 2 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Meraki Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| The Haven2194 · Wadi Al Safa 3 · Majan | Completed | 100% | Jul 2025 Completed | 326 | 219 |
| The Haven II3315 · Wadi Al Safa 3 · Majan | Under construction | 56.3% | Dec 2026 1 mo to go | 225 | 202 |
| The Haven III3876 · Wadi Al Safa 3 · Majan | Under construction | 6.2% | Dec 2027 13 mo to go | 83 | 54 |
| Genesis2044 · Al Barshaa South Third · Arjan | Completed | 100% | Feb 2020 Completed | 200 | 49 |
| Nirvana Residences - I4313 · Me'Aisem First · International Media Production Zone | Not started | 0% | Dec 2028 25 mo to go | 326 | 21 |
| Celeste4586 · Madinat Al Mataar · Dubai South Residential District | Pending | 0% | Jun 2030 43 mo to go | 290 | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 4, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.