DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Metrical Real Estate Development L.L.C متريكل للتطويرالعقاري ش.ذ.م.م DLD developer no. 1283 · Registered with DLD on 27 October 2019 · Licence 842226 10 projects in the DLD register: 7 completed, 2 under construction, 1 not started or pending. 0 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
10
in the DLD register
Completed
7
949 units delivered
Not yet completed
3
692 units in the pipeline
Past DLD end date
0 / 2
under construction with an end date

Delivery record

Projects: 10
Completed 7Under construction 2Not started or pending 1
  • Median time from start to completion: 28 months (7 completed projects).
  • 949 units and villas in completed projects; 692 in projects not yet completed.
  • Completed a month or more after their DLD end date: 0 of 6 completed projects with both dates. In 6 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 0 of 2 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Metrical Real Estate Development L.L.C Most registered sales in the last 24 months first

Projects by Metrical Real Estate Development L.L.C
ProjectDLD status Built DLD end date / completion Units Sales, 24 mo
Leven Residences3555 · Al Barsha South Fifth · Jumeirah Village Triangle Under construction 23.3% Nov 2027 12 mo to go 228 192
The Vyne Residences3094 · Al Barsha South Fifth · Jumeirah Village Triangle Under construction 80.4% Nov 2026 0 mo to go 263 171
The Haven Garden2772 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Apr 2026 Completed 199 68
The Vybe2578 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Sep 2025 Completed 276 63
The Ivy2385 · Al Barsha South Fifth · Jumeirah Village Triangle Completed 100% Jul 2024 Completed 228 44
The Haven Residences2223 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Apr 2022 Completed 161 32
Royal Park South 12365 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Jun 2023 Completed 35 7
S'vn Residences4497 · Al Barsha South Fourth · Jumeirah Village Circle Not started 0% Dec 2028 25 mo to go 201 6
Royal Park2195 · Al Thanyah Fifth · Jumeirah Park Completed 100% Sep 2020 Completed 40 5
Royal Park South2308 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Apr 2023 Completed 10 0

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 3, all pinned

THE VYNE RESIDENCES · 75–100% builtLEVEN RESIDENCES · Under construction, 0–25% builtS'VN RESIDENCES · Not started2 projects2S'VN RESIDENCES · Not startedMakani
Under construction, 0–25% built 75–100% built Not started

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.