Meydan Group (L.L.C) مجموعة ميدان (ش.ذ.م.م) 6 projects in the DLD register: 4 completed, 2 under construction, 0 not started or pending. 0 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 6- Median time from start to completion: 77 months (4 completed projects).
- 798 units and villas in completed projects; 0 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 4 completed projects with both dates. In 4 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 1 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Meydan Group (L.L.C) Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Canal Front Residences-CF7 & CF8 & CF92363 · Al Wasl · Dubai Water Canal | Completed | 100% | Dec 2024 Completed | 374 | 168 |
| Mohammed Bin Rashid Al Maktoum City District One West - Phase 12696 · Ghadeer Al tair | Under construction | 92.6% | — | — | 130 |
| Canal Front Residences-CF3&CF42333 · Al Wasl · Dubai Water Canal | Completed | 100% | Jun 2024 Completed | 105 | 76 |
| Canal Front Residences-CF5&CF62364 · Al Wasl · Dubai Water Canal | Completed | 100% | Sep 2024 Completed | 165 | 73 |
| Mohammed Bin Rashid Al Maktoum City -District One West - Phase 23200 · Ghadeer Al tair | Under construction | 51% | Nov 2027 12 mo to go | — | 39 |
| Canal Front Residences CF1 & CF22315 · Al Wasl · Dubai Water Canal | Completed | 100% | Mar 2024 Completed | 154 | 29 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 2, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.