Mina Rashid Properties L.L.C ميناء راشد العقارية ش.ذ.م.م 22 projects in the DLD register: 2 completed, 15 under construction, 5 not started or pending. 1 of the 11 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 22- 432 units and villas in completed projects; 4,410 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 1 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 1 of 11 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Mina Rashid Properties L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Baystar by VIDA4002 · Madinat Dubai Almelaheyah · Mina Rashid | Under construction | 6.3% | Dec 2029 37 mo to go | 328 | 284 |
| Marina Place 23387 · Madinat Dubai Almelaheyah · Mina Rashid | Under construction | 1.5% | Dec 2028 25 mo to go | 180 | 183 |
| Marina Place 13386 · Madinat Dubai Almelaheyah · Mina Rashid | Under construction | 4.2% | Dec 2028 25 mo to go | 162 | 163 |
| Aurea4115 · Madinat Dubai Almelaheyah · Mina Rashid | Not started | 0.2% | Jun 2030 43 mo to go | 172 | 158 |
| Sera 24032 · Madinat Dubai Almelaheyah · Mina Rashid | Not started | 0% | Nov 2029 36 mo to go | 183 | 112 |
| Seascape2513 · Madinat Dubai Almelaheyah · Mina Rashid | Under construction | 79.1% | Nov 2026 0 mo to go | 395 | 71 |
| Fior 14287 · Madinat Dubai Almelaheyah · Mina Rashid | Not started | 0% | Jul 2030 44 mo to go | 184 | 66 |
| Pier Point 23305 · Madinat Dubai Almelaheyah · Mina Rashid | Under construction | 8.5% | Oct 2028 23 mo to go | 121 | 64 |
| Porto View3306 · Madinat Dubai Almelaheyah · Mina Rashid | Under construction | 6.3% | Oct 2028 23 mo to go | 115 | 64 |
| Seagate2163 · Madinat Dubai Almelaheyah · Mina Rashid | Completed | 100% | Sep 2025 Completed | 302 | 54 |
| Pier Point 13304 · Madinat Dubai Almelaheyah · Mina Rashid | Under construction | 8.3% | Oct 2028 23 mo to go | 122 | 52 |
| Clearpoint2743 · Madinat Dubai Almelaheyah · Mina Rashid | Under construction | 45.1% | — | 478 | 41 |
| Ocean Views3271 · Madinat Dubai Almelaheyah · Mina Rashid | Under construction | 6.2% | Sep 2028 22 mo to go | 78 | 39 |
| Sera 14031 · Madinat Dubai Almelaheyah · Mina Rashid | Not started | 0% | Nov 2029 36 mo to go | 203 | 35 |
| Marina Views3172 · Madinat Dubai Almelaheyah · Mina Rashid | Under construction | 7.1% | Dec 2028 25 mo to go | 554 | 31 |
| Ocean Cove3173 · Madinat Dubai Almelaheyah · Mina Rashid | Under construction | 17.9% | Aug 2028 21 mo to go | 233 | 28 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 20, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.