Myra Real Estate Deveiopment L.L.C مايرا للتطوير العقاري ش.ذ.م.م 5 projects in the DLD register: 4 completed, 1 under construction, 0 not started or pending. 1 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 5- Median time from start to completion: 24 months (4 completed projects).
- 661 units and villas in completed projects; 60 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 4 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 1 of 1 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Myra Real Estate Deveiopment L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Rigel2186 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Mar 2021 Completed | — | 219 | 32 |
| Botanica1649 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Apr 2016 Completed | — | 121 | 31 |
| Myra Onyx4308 · Nad Al Hamar | Under construction | 85.9% | Sep 2026 1 mo past | 1 mo | 60 | 28 |
| Avanos2301 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Nov 2023 Completed | — | 96 | 26 |
| Crystal Residence1752 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Dec 2018 Completed | — | 225 | 25 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 1, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.