Nabni Real Estate Development L.L.C نبني للتطوير العقاري ش.ذ.م.م 6 projects in the DLD register: 4 completed, 2 under construction, 0 not started or pending. 0 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 6- Median time from start to completion: 22 months (4 completed projects).
- 415 units and villas in completed projects; 262 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 3 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 1 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Nabni Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Avenue Residence 7 By Nabni3300 · Jabal Ali First · Al Furjan | Under construction | 17.3% | Oct 2027 11 mo to go | 166 | 126 |
| Avenue Residence 52744 · Jabal Ali First · Al Furjan | Completed | 100% | Oct 2025 Completed | 85 | 35 |
| Avenue Residence 42546 · Jabal Ali First · Al Furjan | Completed | 77.4% | Jan 2024 Completed | 135 | 28 |
| Avenue RESIDENCE11370 · Jabal Ali First · Al Furjan | Completed | 100% | Sep 2014 Completed | 99 | 19 |
| Avenue Residence 21569 · Jabal Ali First · Al Furjan | Completed | 100% | Dec 2015 Completed | 96 | 12 |
| Avenue Residence 62936 · Jabal Ali First · Al Furjan | Under construction | 82.3% | — | 96 | 11 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 2, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.