DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

National Properties Owned By National Bonds Corporation Sole Proprietorship PSC Sole Proprietorship L.L.C الشركة الوطنية العقارية لمالكها شركة الصكوك الوطنية شركة الشخص الواحد مساهمه خاصة شركة الشخص الواحد ش.ذ.م.م DLD developer no. 1149 · Registered with DLD on 21 August 2016 · Licence 592854 6 projects in the DLD register: 3 completed, 1 under construction, 2 not started or pending. 1 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
6
in the DLD register
Completed
3
567 units delivered
Not yet completed
3
375 units in the pipeline
Past DLD end date
1 / 1
under construction with an end date

Delivery record

Projects: 6
Completed 3Under construction 1Not started or pending 2
  • Median time from start to completion: 35 months (3 completed projects).
  • 567 units and villas in completed projects; 375 in projects not yet completed.
  • Completed a month or more after their DLD end date: 1 of 3 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 1 of 1 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by National Properties Owned By National Bonds Corporation Sole Proprietorship PSC Sole Proprietorship L.L.C Most registered sales in the last 24 months first

Projects by National Properties Owned By National Bonds Corporation Sole Proprietorship PSC Sole Proprietorship L.L.C
ProjectDLD status Built DLD end date / completion Past DLD end date Units Sales, 24 mo
Casa Flores And Eden Apartments1853 · Al Hebiah First · Motor City Completed 100% Jun 2019 Completed— 273 182
161 Jumeirah Lane3084 · Al Satwa · Jumeirah Garden City Under construction 70% Mar 2026 8 mo past8 mo 161 137
399 Hills Park B2510 · Hadaeq Sheikh Mohammed Bin Rashid · Dubai Hills Estate Completed 100% Aug 2026 Completed— 199 46
Green Community Motor City, Phase Ii - Casa Familia1788 · Al Hebiah First · Motor City Completed 100% Nov 2017 Completed— 95 15
Project 4431, Al Barshaa South Third4431 · Al Barshaa South Third · Arjan Pending 0% Feb 2028 15 mo to go— — 0
399 Hills Park A2509 · Hadaeq Sheikh Mohammed Bin Rashid · Dubai Hills Estate Pending 0% — — 214 0

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 3, all pinned

399 Hills Park A · Not started161 Jumeirah Lane · 50–75% builtProject 4431 · Not started399 Hills Park A · Not started161 Jumeirah Lane · 50–75% builtProject 4431 · Not startedMakani
50–75% built Not started

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.