New World Developments L.L.C نيو ورلد ديفيلوبمينتدس ش.ذ.م.م 6 projects in the DLD register: 5 completed, 1 under construction, 0 not started or pending. 0 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 6- Median time from start to completion: 53 months (5 completed projects).
- 184 units and villas in completed projects; 70 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 3 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 1 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by New World Developments L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Marwa Heights2062 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Jul 2023 Completed | 128 | 39 |
| Marwa Homes Iii2804 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Jul 2026 Completed | 14 | 11 |
| Marwa Homes Iv2807 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Dec 2025 Completed | 12 | 9 |
| Marwa Homes1562 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Jul 2015 Completed | 14 | 2 |
| Marwa Homes 21744 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Feb 2018 Completed | 16 | 2 |
| Marwa Views3773 · Al Barsha South Fifth · Jumeirah Village Triangle | Under construction | 40.1% | Mar 2027 4 mo to go | 70 | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 1, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.