Nshama Properties Owned By Nshmi Development One Person Company L.L.C نشاما للعقارات لمالكها نشمي ديفلوبمنت شركة الشخص الواحد ش.ذ.م.م 39 projects in the DLD register: 16 completed, 17 under construction, 6 not started or pending. 0 of the 12 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 39- Median time from start to completion: 26 months (16 completed projects).
- 4,947 units and villas in completed projects; 4,236 in projects not yet completed.
- Completed a month or more after their DLD end date: 2 of 13 completed projects with both dates. In 9 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 12 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Nshama Properties Owned By Nshmi Development One Person Company L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Maha Townhouses2490 · Al Yelayiss 2 · Town Square | Completed | 100% | Aug 2025 Completed | 500 | 250 |
| Rosewell4149 · Al Yelayiss 2 · Town Square | Not started | 0% | Dec 2028 25 mo to go | 217 | 178 |
| Rawda Apartments1836 · Al Yelayiss 2 · Town Square | Completed | 100% | Feb 2020 Completed | 748 | 175 |
| Evelyn on the Park4150 · Al Yelayiss 2 · Town Square | Not started | 0% | Feb 2029 27 mo to go | 259 | 172 |
| The Baltimore3365 · Al Yelayiss 2 · Town Square | Under construction | 26.3% | Sep 2027 10 mo to go | 167 | 167 |
| Odessa3450 · Al Yelayiss 2 · Town Square | Under construction | 8% | Dec 2027 13 mo to go | 178 | 167 |
| Liva2492 · Al Yelayiss 2 · Town Square | Completed | 100% | Sep 2025 Completed | 484 | 165 |
| Augusta3649 · Al Yelayiss 2 · Town Square | Under construction | 5.3% | Jan 2028 14 mo to go | 154 | 143 |
| Lexington3364 · Al Yelayiss 2 · Town Square | Under construction | 4.5% | Sep 2027 10 mo to go | 142 | 139 |
| Berkshire Park3312 · Al Yelayiss 2 · Town Square | Under construction | 17.6% | Jun 2027 7 mo to go | 149 | 137 |
| Ellison3451 · Al Yelayiss 2 · Town Square | Under construction | 40.2% | Nov 2027 12 mo to go | 148 | 137 |
| Olbia3749 · Al Yelayiss 2 · Town Square | Not started | 0% | May 2028 18 mo to go | 156 | 134 |
| Camden3839 · Al Yelayiss 2 · Town Square | Under construction | 7.2% | Mar 2028 16 mo to go | 168 | 130 |
| Alton3685 · Al Yelayiss 2 · Town Square | Under construction | 5.2% | May 2028 18 mo to go | 149 | 119 |
| The Hamilton2700 · Al Yelayiss 2 · Town Square | Completed | 100% | Dec 2025 Completed | 242 | 117 |
| The Regent2525 · Al Yelayiss 2 · Town Square | Completed | 100% | Jul 2025 Completed | 238 | 116 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 23, 22 pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.