Object One Real Estate Development L.L.C اوبجيكت ون للتطوير العقاري ش.ذ.م.م 16 projects in the DLD register: 2 completed, 10 under construction, 4 not started or pending. 1 of the 7 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 16- 321 units and villas in completed projects; 3,710 in projects not yet completed.
- Completed a month or more after their DLD end date: 2 of 2 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 1 of 7 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Object One Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Essenlife Residence3639 · Al Barsha South Fifth · Jumeirah Village Triangle | Under construction | 7.2% | Mar 2028 16 mo to go | — | 357 | 288 |
| Alta View Skyhomes3842 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 5.8% | Jun 2029 31 mo to go | — | 507 | 243 |
| ELARIS Sky4019 · Al Barsha South Fifth · Jumeirah Village Triangle | Not started | 0.2% | Sep 2028 22 mo to go | — | 409 | 239 |
| The Fifth Tower3048 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 50.3% | Jul 2026 3 mo past | 3 mo | 345 | 197 |
| Vistara House3448 · Jabal Ali First · Al Furjan | Under construction | 7% | Mar 2027 4 mo to go | — | 141 | 109 |
| Ozone 1 Residence2977 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 56.8% | — | — | 272 | 99 |
| Aurelia Residence3768 · Al Hebiah Fourth · Dubai Sports City | Under construction | 4.5% | Mar 2028 16 mo to go | — | 280 | 96 |
| 1WOOD Residence2907 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 93.7% | — | — | 227 | 94 |
| V1TER Residence2710 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Jul 2026 Completed | — | 175 | 85 |
| RA1N Residence2635 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Mar 2026 Completed | — | 146 | 76 |
| ELARIS Rise4018 · Al Barsha South Fifth · Jumeirah Village Triangle | Under construction | 1.7% | Sep 2028 22 mo to go | — | 214 | 64 |
| Winner Tower2991 · Al Barsha South Fifth · Jumeirah Village Triangle | Under construction | 27.8% | — | — | 138 | 41 |
| 1WOOD Residence 24435 · Al Barsha South Fourth · Jumeirah Village Circle | Not started | 0% | Oct 2027 11 mo to go | — | 209 | 22 |
| Sky Level 14486 · Al Barsha South Fourth · Jumeirah Village Circle | Not started | 0% | Feb 2029 27 mo to go | — | 440 | 7 |
| Elaris Axis4212 · Al Barsha South Fifth · Jumeirah Village Triangle | Under construction | 2.2% | Nov 2028 24 mo to go | — | 171 | 4 |
| Project 4343, Palm Deira4343 · Palm Deira | Pending | 0% | Feb 2028 15 mo to go | — | — | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 14, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.