Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Orchid Living Real Estate L.L.C اوركيد ليفينج للعقارات ش.ذ.م.م DLD developer no. 2401 · Registered with DLD on 13 June 2025 · Licence 1085909 1 projects in the DLD register: 0 completed, 1 under construction, 0 not started or pending. 1 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
1
in the DLD register
Completed
0
0 units delivered
Not yet completed
1
44 units in the pipeline
Past DLD end date
1 / 1
under construction with an end date

Delivery record

Projects: 1
Under construction 1
  • 0 units and villas in completed projects; 44 in projects not yet completed.
  • Under construction past their DLD end date: 1 of 1 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Orchid Living Real Estate L.L.C Most registered sales in the last 24 months first

Projects by Orchid Living Real Estate L.L.C
ProjectDLD status Built DLD end date Past DLD end date Units Sales, 24 mo
Orchid Residence 14054 · Madinat Al Mataar · Dubai South Residential District Under construction 48.5% Mar 2026 7 mo past7 mo 44 1

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 1, all pinned

Orchid Residence 1 · 25–50% builtOrchid Residence 1 · 25–50% builtMakani
25–50% built

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.