DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Park 1 L.L.C بارك 1 ش.ذ.م.م DLD developer no. 1203 · Registered with DLD on 24 July 2017 · Licence 750308 7 projects in the DLD register: 2 completed, 3 under construction, 2 not started or pending. 0 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
7
in the DLD register
Completed
2
1,522 units delivered
Not yet completed
5
2,576 units in the pipeline
Past DLD end date
0 / 2
under construction with an end date

Delivery record

Projects: 7
Completed 2Under construction 3Not started or pending 2
  • 1,522 units and villas in completed projects; 2,576 in projects not yet completed.
  • Completed a month or more after their DLD end date: 0 of 2 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 0 of 2 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Park 1 L.L.C Most registered sales in the last 24 months first

Projects by Park 1 L.L.C
ProjectDLD status Built DLD end date / completion Units Sales, 24 mo
Avenue Park Towers3337 · Al Kifaf · Wasl 1 Under construction 7.7% Dec 2028 25 mo to go 671 485
Park Views Residences A2630 · Al Kifaf · Wasl 1 Under construction 95.5% — 615 338
1 Residences2368 · Al Kifaf · Wasl 1 Completed 100% Sep 2022 Completed 758 173
Park Views Residences B2576 · Al Kifaf · Wasl 1 Under construction 98.8% Mar 2027 4 mo to go 476 152
Park Gate Residences1957 · Al Kifaf · Wasl 1 Completed 100% Oct 2020 Completed 764 99
Avenue Park Towers II4496 · Al Kifaf · Wasl 1 Not started 0% Mar 2030 40 mo to go 596 90
Nine Collective4315 · Al Kifaf · Wasl 1 Not started 0% Apr 2030 41 mo to go 218 0

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 5, all pinned

5 projects55 projects5Makani
Under construction, 0–25% built 75–100% built Not started

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.