Pinnacle A K S Real Estate Development L.L.C بيناكل ايه كي اس لتطوير العقاري ذ.م.م 2 projects in the DLD register: 0 completed, 2 under construction, 0 not started or pending. 1 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 2- 0 units and villas in completed projects; 269 in projects not yet completed.
- Under construction past their DLD end date: 1 of 2 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Pinnacle A K S Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Vitalia by Pinnacle3022 · Palm Jumeirah | Under construction | 12.3% | Jun 2026 4 mo past | 4 mo | 45 | 22 |
| Sartoria3853 · Al Hebiah Fourth · Dubai Sports City | Under construction | 51.2% | Oct 2027 11 mo to go | — | 224 | 3 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 2, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.