Prescott Real Estate Development L.L.C بريسكوت للتطوير العقاري ذ.م.م 11 projects in the DLD register: 5 completed, 5 under construction, 1 not started or pending. 0 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 11- Median time from start to completion: 39 months (5 completed projects).
- 815 units and villas in completed projects; 1,466 in projects not yet completed.
- Completed a month or more after their DLD end date: 2 of 5 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 2 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Prescott Real Estate Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Legado By Prescott3210 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 23.3% | Aug 2027 9 mo to go | 343 | 342 |
| Verano By Prescott3339 · Al Hebiah Second · Dubai Studio City | Under construction | 41.1% | Dec 2026 1 mo to go | 269 | 231 |
| Prime Residency 32276 · Jabal Ali First · Al Furjan | Completed | 100% | Dec 2024 Completed | 292 | 135 |
| The Caden By Prescott4215 · Bukadra | Not started | 0.5% | May 2028 18 mo to go | 229 | 107 |
| ELEVATE by Prescott2566 · Al Barshaa South Third · Arjan | Completed | 100% | Jun 2026 Completed | 223 | 107 |
| Fairway Residences By Prescott3086 · Al Hebiah Fourth · Dubai Sports City | Under construction | 50% | — | 156 | 102 |
| Serene Gardens by Prescott2740 · Jabal Ali First · Discovery Gardens | Under construction | 61.7% | — | 184 | 37 |
| Prime Gardens2416 · Al Barshaa South Third · Arjan | Completed | 100% | Apr 2024 Completed | 139 | 36 |
| Prime Views1961 · Nad Al Shiba First · Meydan Racecourse Community | Completed | 100% | Mar 2021 Completed | 153 | 33 |
| Serene Gardens 2 by Prescott2872 · Jabal Ali First · Discovery Gardens | Under construction | 70% | — | 285 | 26 |
| Prime Townhouses2362 · Jabal Ali First · Al Furjan | Completed | 100% | Sep 2022 Completed | 8 | 1 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 6, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.