DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Qube Development L.L.C كيوب للتطوير ذ.م.م DLD developer no. 1692 · Registered with DLD on 23 August 2023 · Licence 1043390 5 projects in the DLD register: 1 completed, 2 under construction, 2 not started or pending. 0 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
5
in the DLD register
Completed
1
72 units delivered
Not yet completed
4
880 units in the pipeline
Past DLD end date
0 / 2
under construction with an end date

Delivery record

Projects: 5
Completed 1Under construction 2Not started or pending 2
  • 72 units and villas in completed projects; 880 in projects not yet completed.
  • Completed a month or more after their DLD end date: 1 of 1 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 0 of 2 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Qube Development L.L.C Most registered sales in the last 24 months first

Projects by Qube Development L.L.C
ProjectDLD status Built DLD end date / completion Units Sales, 24 mo
Arisha Terraces3216 · Al Hebiah Second · Dubai Studio City Under construction 34% Oct 2027 11 mo to go 420 334
Cubix Residences2812 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Mar 2026 Completed 72 35
Elire3467 · Business Bay Under construction 8.2% Dec 2028 25 mo to go 101 3
Sawa Residences4565 · Ras Al Khor Industrial First Not started 0% Jul 2030 44 mo to go 359 0
Project 4473, Wadi Al Safa 24473 · Wadi Al Safa 2 · Falcon City Pending 0% Oct 2031 59 mo to go — 0

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 4, all pinned

Arisha Terraces · 25–50% builtElire · Under construction, 0–25% builtProject 4473 · Not startedSawa Residences · Not startedArisha Terraces · 25–50% builtElire · Under construction, 0–25% builtProject 4473 · Not startedSawa Residences · Not startedMakani
Under construction, 0–25% built 25–50% built Not started Approximate location (ringed)

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.