Samana Si Holding Limited Dubai Branch سمانا إس آي هولدينج ليمتد فرع دبى 5 projects in the DLD register: 1 completed, 4 under construction, 0 not started or pending. 3 of the 3 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 5- 93 units and villas in completed projects; 663 in projects not yet completed.
- Completed a month or more after their DLD end date: 1 of 1 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 3 of 3 projects with an end date, by a median of 6 months.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Samana Si Holding Limited Dubai Branch Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Samana Waves2345 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 90.6% | Apr 2026 6 mo past | 6 mo | 197 | 41 |
| Samana Waves 22574 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 52.1% | Mar 2026 7 mo past | 7 mo | 173 | 17 |
| California by SD2666 · Jabal Ali First · Discovery Gardens | Under construction | 24.5% | — | — | 178 | 11 |
| Miami By Sd2454 · Al Barsha South Fifth · Jumeirah Village Triangle | Under construction | 71.3% | Jul 2026 3 mo past | 3 mo | 115 | 10 |
| Samana Miami2433 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Jun 2026 Completed | — | 93 | 4 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 4, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.