Select Global Development L.L.C سيلكت جلوبال ديفيلوبمنت ش.ذ.م.م 19 projects in the DLD register: 14 completed, 3 under construction, 2 not started or pending. DLD projects register, export of 1 November 2026
Delivery record
Projects: 19- Median time from start to completion: 42 months (14 completed projects).
- 6,911 units and villas in completed projects; 1,374 in projects not yet completed.
- Completed a month or more after their DLD end date: 6 of 14 completed projects with both dates. In 7 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Select Global Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Peninsula Four2461 · Business Bay | Completed | 100% | Jun 2026 Completed | 1,038 | 333 |
| Peninsula Three2372 · Business Bay | Completed | 100% | Dec 2025 Completed | 859 | 303 |
| The EDGE2611 · Business Bay | Completed | 100% | Aug 2026 Completed | 1,030 | 259 |
| Peninsula One2284 · Business Bay | Completed | 100% | Apr 2024 Completed | 525 | 192 |
| Peninsula Two2318 · Business Bay | Completed | 100% | Feb 2026 Completed | 462 | 179 |
| Peninsula Five2344 · Business Bay | Completed | 100% | Dec 2024 Completed | 383 | 165 |
| Artistry One Residences4259 · Zaabeel Second · Business Park | Not started | 0% | Feb 2029 27 mo to go | 232 | 156 |
| 15 Northside2214 · Business Bay | Completed | 100% | Apr 2023 Completed | 358 | 96 |
| Six Senses Residences Dubai Marina3006 · Marsa Dubai · Dubai Marina | Under construction | 26.7% | — | 251 | 93 |
| The Residences At Marina Gate 21547 · Marsa Dubai · Dubai Marina | Completed | 100% | Feb 2019 Completed | 535 | 88 |
| Jumeirah Living Marina Gate1743 · Marsa Dubai · Dubai Marina | Completed | 100% | Jun 2020 Completed | 418 | 85 |
| Studio One1776 · Marsa Dubai · Dubai Marina | Completed | 100% | Sep 2019 Completed | 410 | 80 |
| Artistry Two Residences4261 · Zaabeel Second · Business Park | Not started | 0% | Feb 2029 27 mo to go | 235 | 62 |
| The Residences At Marina Gate 11495 · Marsa Dubai · Dubai Marina | Completed | 100% | Apr 2018 Completed | 415 | 43 |
| No 91394 · Marsa Dubai · Dubai Marina | Completed | 100% | Dec 2017 Completed | 223 | 36 |
| Six Senses Residences The Palm, Dubai2350 · Palm Jumeirah | Completed | 100% | Sep 2026 Completed | 173 | 35 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 5, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.