DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Tabeer Real Estate Development L.L.C تعبير للتطوير العقاري ش.ذ.م.م DLD developer no. 1062 · Registered with DLD on 25 February 2015 · Licence 711824 6 projects in the DLD register: 3 completed, 2 under construction, 1 not started or pending. 1 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
6
in the DLD register
Completed
3
414 units delivered
Not yet completed
3
486 units in the pipeline
Past DLD end date
1 / 2
under construction with an end date

Delivery record

Projects: 6
Completed 3Under construction 2Not started or pending 1
  • Median time from start to completion: 32 months (3 completed projects).
  • 414 units and villas in completed projects; 486 in projects not yet completed.
  • Completed a month or more after their DLD end date: 1 of 3 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 1 of 2 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Tabeer Real Estate Development L.L.C Most registered sales in the last 24 months first

Projects by Tabeer Real Estate Development L.L.C
ProjectDLD status Built DLD end date / completion Past DLD end date Units Sales, 24 mo
48 Parkside2831 · Al Barshaa South Third · Arjan Completed 100% May 2026 Completed— 187 139
Parkside Boulevard3326 · Al Barshaa South Third · Arjan Under construction 51.9% Dec 2027 13 mo to go— 171 128
368 Park Ln4176 · Al Barsha South Fourth · Jumeirah Village Circle Not started 0% Aug 2028 21 mo to go— 213 114
99 Park Place2968 · Al Barsha South Fourth · Jumeirah Village Circle Under construction 90% Dec 2025 10 mo past10 mo 102 54
Dragon View1634 · Al Warsan First · International City Phase 1 Completed 100% May 2016 Completed— 120 17
Tabeer 12090 · Al Warsan First · International City Phase 1 Completed 100% Jun 2022 Completed— 107 10

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 3, all pinned

99 PARK PLACE · 75–100% builtParkside Boulevard · 50–75% built368 Park Ln · Not started99 PARK PLACE · 75–100% builtParkside Boulevard · 50–75% built368 Park Ln · Not startedMakani
50–75% built 75–100% built Not started

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.