Tameer Holding Investment (LLC) تعمير القابضة للاستثمار (ش.ذ.م.م) 7 projects in the DLD register: 7 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026
Projects
7
in the DLD register
Completed
7
3,325 units delivered
Not yet completed
0
0 units in the pipeline
Delivery record
Projects: 7Completed 7
- Median time from start to completion: 52 months (7 completed projects).
- 3,325 units and villas in completed projects; 0 in projects not yet completed.
- Completed a month or more after their DLD end date: 2 of 7 completed projects with both dates. In 5 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Tameer Holding Investment (LLC) Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Princess Tower221 · Marsa Dubai · Dubai Marina | Completed | 100% | Jul 2012 Completed | 771 | 121 |
| Elite Residence227 · Marsa Dubai · Dubai Marina | Completed | 100% | Jul 2012 Completed | 700 | 118 |
| Imperial Residence210 · Al Barsha South Fifth · Jumeirah Village Triangle | Completed | 100% | Jun 2014 Completed | 539 | 102 |
| Palace Tower213 · Nadd Hessa · Silicon Oasis | Completed | 100% | Aug 2009 Completed | 597 | 81 |
| Al Jawzaa214 · Warsan Fourth · International City Phase 3 | Completed | 100% | Mar 2012 Completed | 186 | 33 |
| Silver Tower219 · Business Bay | Completed | 100% | Aug 2011 Completed | 265 | 0 |
| Regal Tower220 · Business Bay | Completed | 100% | Dec 2012 Completed | 267 | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.