Tanmiyat Global Real Estate Development L L C تنميات جلوبل للتطوير العقاري ش ذ م م 6 projects in the DLD register: 5 completed, 1 under construction, 0 not started or pending. 1 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 6- Median time from start to completion: 44 months (5 completed projects).
- 462 units and villas in completed projects; 343 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 5 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 1 of 1 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Tanmiyat Global Real Estate Development L L C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Living Legends Phase 71326 · Wadi Al Safa 3 · Living Legends | Under construction | 91.9% | Sep 2021 61 mo past | 61 mo | 343 | 44 |
| Living Legends Phase 31322 · Wadi Al Safa 3 · Living Legends | Completed | 100% | Apr 2015 Completed | — | 1 | 36 |
| Living Legends Phase 21321 · Wadi Al Safa 3 · Living Legends | Completed | 100% | Apr 2015 Completed | — | — | 21 |
| The Court488 · Business Bay | Completed | 100% | Mar 2021 Completed | — | 271 | 21 |
| Living Legends Phase 1489 · Wadi Al Safa 3 · Living Legends | Completed | 100% | Apr 2015 Completed | — | 2 | 19 |
| The Exchange490 · Business Bay | Completed | 100% | Oct 2015 Completed | — | 188 | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 1, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.