DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Tanmiyat Global Real Estate Development L L C تنميات جلوبل للتطوير العقاري ش ذ م م DLD developer no. 905 · Registered with DLD on 29 January 2011 · Licence 641585 6 projects in the DLD register: 5 completed, 1 under construction, 0 not started or pending. 1 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
6
in the DLD register
Completed
5
462 units delivered
Not yet completed
1
343 units in the pipeline
Past DLD end date
1 / 1
under construction with an end date

Delivery record

Projects: 6
Completed 5Under construction 1
  • Median time from start to completion: 44 months (5 completed projects).
  • 462 units and villas in completed projects; 343 in projects not yet completed.
  • Completed a month or more after their DLD end date: 0 of 5 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 1 of 1 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Tanmiyat Global Real Estate Development L L C Most registered sales in the last 24 months first

Projects by Tanmiyat Global Real Estate Development L L C
ProjectDLD status Built DLD end date / completion Past DLD end date Units Sales, 24 mo
Living Legends Phase 71326 · Wadi Al Safa 3 · Living Legends Under construction 91.9% Sep 2021 61 mo past61 mo 343 44
Living Legends Phase 31322 · Wadi Al Safa 3 · Living Legends Completed 100% Apr 2015 Completed— 1 36
Living Legends Phase 21321 · Wadi Al Safa 3 · Living Legends Completed 100% Apr 2015 Completed— — 21
The Court488 · Business Bay Completed 100% Mar 2021 Completed— 271 21
Living Legends Phase 1489 · Wadi Al Safa 3 · Living Legends Completed 100% Apr 2015 Completed— 2 19
The Exchange490 · Business Bay Completed 100% Oct 2015 Completed— 188 0

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 1, all pinned

LIVING LEGENDS PHASE 7 · 75–100% builtLIVING LEGENDS PHASE 7 · 75–100% builtMakani
75–100% built Approximate location (ringed)

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.